Hungary’s Ministry of Transport announced that the second phase of the M49 expressway will proceed toward the Romanian border, securing a gross 190 milliárd forint investment to connect the M3 motorway to Szatmárnémeti by June 30, 2029, after restructuring an inherited funding shortfall.
The 45-kilometer, dual two-lane expressway project will bypass Mátészalka and lead directly to Csenger before crossing into Romania, where a brand-new border-crossing point will be established. The initial stretch running from the M3 motorway to Ököritófülpös is slated for completion this autumn, while the remaining corridor leading to the border must be finished by June 30, 2029.
Financial Restructuring Salvages the 190 milliárd Forint Project
Ministry leadership revealed that although a construction contract with Duna Aszfalt had been in place since 2024, the gross 190 milliárd forint investment lacked stable backing. Funding had previously been diverted to the Mohács Danube bridge project, and land acquisition and site preparation dragged on for more than three years due to earlier budgetary restrictions. The financial realignment was designed to prevent penalty interest payments while construction was already underway without sufficient budget coverage behind incoming invoices.
“the previous irresponsible decisions would have favored only the contractor, because if the ministry could not pay the invoices, we could even have had to pay penalty interest.”
Ministry of Transport, via Infostart
State leaders emphasized that abandoning the corridor to leave unfinished fragments was unacceptable, prompting the rescheduled timeline to ensure the highway reaches completion by the middle of 2029. At the same time, officials noted that inherited investments across the central budget place a heavy burden on upcoming fiscal cycles.
Budget Pressures and Cross-Border Alignment With Romania
The financial commitments tied to inherited transport projects such as the M49 and the Mohács bridge network require hundreds of billions of forints in the central budget even before considering newly initiated developments. Officials stated that despite these fiscal constraints, the government is actively searching for resources to fund long-delayed maintenance across the national road network.

“It is important to see that in the central budget of the next 2-3 years, inherited investments represent significant expenditures, whether it is the M49 or the Mohács bridge and its related road network.”
Ministry of Transport, via Infostart
Across the border, coordination remains vital. Romania is actively advancing its connecting infrastructure, having already signed a construction contract for a high-speed road stretching between Szatmárnémeti and Óvár, with completion targeted for the spring of 2029. Together, the synchronized developments establish a direct high-speed connection linking Szabolcs-Szatmár-Bereg county with Northern Transylvania.
Broader Concessions Disquiet and Infrastructure Tradeoffs
The announcement arrived unexpectedly amid broader turmoil in Hungary’s state development sector. Following the state’s cancellation of its 35-year concession contract with MKIF, several other high-profile highway developments face potential multi-year delays, including the ongoing expansion of the M1 motorway alongside plans for the M200 and M8 expressways and the upcoming M7 expansion.